Reading: ‘The Flight Deck Was Too Short’: France Took 14 Years to Build Its Only Nuclear Aircraft Carrier and the Propeller Fell Off
Share
Notification Show More
Font ResizerAa
Font ResizerAa
Concealed RepublicanConcealed Republican
  • News
  • Guns
  • Politics
  • Videos
  • Home
  • Latest News
  • Guns
  • Politics
  • Videos
Have an existing account? Sign In
Follow US
  • Advertise
  • Advertise
© 2022 Foxiz News Network. Ruby Design Company. All Rights Reserved.
Concealed Republican > Blog > News > ‘The Flight Deck Was Too Short’: France Took 14 Years to Build Its Only Nuclear Aircraft Carrier and the Propeller Fell Off
News

‘The Flight Deck Was Too Short’: France Took 14 Years to Build Its Only Nuclear Aircraft Carrier and the Propeller Fell Off

News Room
Last updated: September 26, 2026 1:04 am
By News Room 8 Min Read
Share
‘The Flight Deck Was Too Short’: France Took 14 Years to Build Its Only Nuclear Aircraft Carrier and the Propeller Fell Off
SHARE

Summary and Key Points: France wanted a nuclear aircraft carrier so it would never have to depend on land bases or allied decks to project air power. It got one, the Charles de Gaulle, the only nuclear-powered carrier outside the U.S. Navy. But the second ship France planned was never built because the first one cost so much, so whenever the Charles de Gaulle is in the shipyard, France has no carrier at all. Now Paris is planning a successor, and the first ship’s troubled birth serves as a cautionary tale.

Charles de Gaulle: France’s Problem Child Aircraft Carrier 

Charles de Gaulle is France’s only aircraft carrier, the flagship of the French Navy, and the only nuclear-powered aircraft carrier outside of the US Navy. But getting her into service was not smooth. Ordered at the end of the Cold War to replace the aging Clemenceau-class carriers, construction began in 1987. She was launched in 1994 but didn’t enter formal service until 2001, a full 14 years after construction began.

During that 14-year stretch, the project encountered several problems, including a shifting strategic environment, budget pressure, construction delays, propulsion problems, and propeller failure.

U.S. 5TH FLEET AREA OF OPERATIONS (April 24, 2019) A U.S. Marine MV-22 Osprey assigned to the 22nd Marine Expeditionary Unit sits on the flight deck of France’s Marine Nationale aircraft carrier FS Charles De Gaulle (R 91). This was the second time that Ospreys have landed aboard the French vessel. Marines and Sailors assigned to the 22nd MEU and Kearsarge Amphibious Ready Group are currently deployed to the U.S. 5th Fleet area of operations in support of naval operations to ensure maritime stability and security in the Central region, connecting the Mediterranean and the Pacific through the western Indian Ocean and three strategic choke points. (U.S. Marine Corps photo by Maj. Joshua Smith/Released)

France’s Charles de Gaulle Carrier: Prestige Amid Challenges

French Aircraft Carrier Charles de Gaulle.

Charles de Gaulle eventually became an impressive symbol of French autonomy, but building her was truly an ordeal.

Pushing for Nuclear

France wanted a nuclear carrier.

Having operated the Clemenceau and Foch since the early 1960s, France needed a replacement by the 1980s.

France wanted to preserve its ability to operate independent carrier aviation rather than rely on land bases or allied carrier decks.

France was attracted to nuclear propulsion for its incredible endurance, sustained high-speed operations, and the increased strategic independence it provides.

Originally, the plan called for the construction of two carriers.

But the second ship was never built because of the first ship’s costs. That decision would reverberate as an availability problem, still felt today.

Compromising on Propulsion

Rather than designing clean-sheet naval reactors, France adapted the K15 reactors already in use aboard French ballistic-missile submarines.

So the Charles de Gaulle uses two K15 pressurized-water reactors, which are great in terms of commonality and cost, but because the reactors were originally designed for a much smaller submarine, they are underpowered for a carrier of de Gaulle’s size.

The ship measures 858 feet long and displaces 42,000 tons.

With the K15 reactor, the top speed is only about 27 knots—considerably slower than American nuclear supercarriers, which can exceed 30 knots.

Speed matters because carriers steaming into the wind contribute to the airflow needed to launch and recover aircraft.

France would eventually compensate with catapult and operational tweaks, but the propulsion choice illustrates a compromise at the heart of the massive project.

Budget Constriction

Construction began shortly before the Cold War ended. Naturally, when the Cold War did end, the French defense budget came under pressure.

Construction of de Gaulle was stopped and started multiple times as funding was stretched.

Ironically, delays increased the overall project cost, as workforce retention costs, shipyard overheads, and changing equipment requirements mounted.

The carrier was eventually launched in 1994, but it would still require years of fitting and testing.

The initial expectation was that the ship would enter service much earlier than its eventual commissioning in 2001.

But perhaps this was all to be expected.

The Charles de Gaulle wasn’t merely a ship that France was building; it was an entire nuclear carrier ecosystem being built from scratch.

Ongoing Problems

At sea, de Gaulle encountered several time-consuming problems.

One involved the flight deck, which was intended to launch both the Dassault Rafale M and E-2C Hawkeye.

Dassault Rafale Fighter

Dassault Rafale Fighter. Image Credit: Creative Commons.

But a problem emerged whereby the existing flight deck arrangement and length were inadequate for safe E-2C operations.

So the flight deck had to be extended by roughly 14 feet.

Obviously, this was a topic of immense criticism: the flight deck was too short for one of the two aircraft the project was designed to accommodate.

The carrier also experienced excessive vibration under certain operating conditions.

This wasn’t trivial—it affected crew habitability, machinery life, sensitive electronics, and aviation operations.

Testing isolated the problem, and changes were made, but it was another example of the project’s shortcomings.

And then in November 2000, the propeller broke.

This forced the ship back to port for repairs and prompted an investigation into quality issues.

France reportedly resorted to temporarily using propellers from older Clemenceau-era equipment, which further reduced performance and delayed operational deployment.

In the end, France commissioned its carrier, launching the only non-US nuclear carrier.

Today, after two decades of operation, the Charles de Gaulle is still serving admirably, though a replacement has been planned: the PANG next-generation carrier, also known as France Libre.

PANG France Nuclear Aircraft Carrier

PANG France Nuclear Aircraft Carrier. Image Credit: French Government.

PANG Aircraft Carrier French Navy

PANG Aircraft Carrier French Navy Photo.

PANG Aircraft Carrier from France.

PANG Aircraft Carrier from France. Image Credit: Industry Handout.

About the Author: Harrison Kass

Harrison Kass is a writer and attorney focused on national security, technology, and political culture. His work has appeared in Tablet, City Journal, The Hill, The Spectator, and The Cipher Brief. He holds a JD from the University of Oregon and a master’s in Global & Joint Program Studies from NYU. More at harrisonkass.com.

You Might Also Like

Sen Josh Hawley investigates Flock Safety AI surveillance network

California Home Invader Disarmed by Resident, Killed With Own Gun

Olympic champion Nancy Hogshead honored for advocacy as she pushes WNBA on female eligibility rules

Longtime Tennessee commissioner arrested for shocking sex crimes against children

‘It was almost like a missile’: Good Samaritans rush to save Florida woman from alligator — but a devastating price was paid

Share This Article
Facebook X Email Print
Previous Article Mikie Sherrill Finds One Jersey Man She Wanted Gone – Her Lt Gov Resigns Mikie Sherrill Finds One Jersey Man She Wanted Gone – Her Lt Gov Resigns
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

- Advertisement -
Ad image

Latest News

Mikie Sherrill Finds One Jersey Man She Wanted Gone – Her Lt Gov Resigns
Mikie Sherrill Finds One Jersey Man She Wanted Gone – Her Lt Gov Resigns
Politics
‘NEVER going to happen’: DHS Sec. Mullin CRUSHES ‘open borders’ Democrat pushing ‘radical’ anti-ICE bill
‘NEVER going to happen’: DHS Sec. Mullin CRUSHES ‘open borders’ Democrat pushing ‘radical’ anti-ICE bill
News
Fulton Sheen nears sainthood as his message resonates today: Michael Knowles
Fulton Sheen nears sainthood as his message resonates today: Michael Knowles
News
H2Go USB or Solar Water Purifier for “Unlimited” Water Treatment – reThinkSurvival.com
H2Go USB or Solar Water Purifier for “Unlimited” Water Treatment – reThinkSurvival.com
News
The US Air Force Built 195 F-22s Instead of 750 and Destroyed the Tooling to Make More — Now China Has Exactly the Air Force the Raptor Was Designed to Defeat
The US Air Force Built 195 F-22s Instead of 750 and Destroyed the Tooling to Make More — Now China Has Exactly the Air Force the Raptor Was Designed to Defeat
News
RAF Pilots Eject Moments Before Training Jet’s Fiery Crash in Wales [WATCH]
RAF Pilots Eject Moments Before Training Jet’s Fiery Crash in Wales [WATCH]
Politics
© 2025 Concealed Republican. All Rights Reserved.
  • Privacy Policy
  • Terms of use
  • Press Release
  • Advertise
  • Contact
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?